Finnish builder Jatke to construct 70MW data centre for AI firm Nebius

A Finnish construction group has begun work on a second data centre in Mäntsälä for the AI cloud company Nebius, with up to 400 people expected on site at the peak of construction.

Martti Asikainen | 23.11.2026 | Photo by Nebius

Nebius data center - photoshoot at Mäntsälä, Finland 13th May 2025. Photo by Nebius.

Jatke Toimitilat, part of the Jatke group, is carrying out the groundworks and building-services work on the facility. Once finished, the site is expected to have a capacity of 70 megawatts (MW). Groundworks began in the summer. Neither the value of the contract nor the completion date has been disclosed.

The data centre is being built on a prepared plot in the Kapuli industrial area of Mäntsälä, about 50km (30 miles) north of Helsinki. The area is meant for large operators and already has data centres, some completed and some under construction. Its infrastructure is designed for energy-intensive users.

It will be Nebius’s second data centre in Finland. Its first is also in Mäntsälä.

"Significant opening"

The project is Jatke’s first data centre contract. The group’s chief executive, Hannu Anttonen, described it as a significant step into data centre construction.

Antti Raunemaa, chief executive of Jatke Toimitilat, said he was delighted the company could now show its expertise in the sector. He said the job would demand a tight schedule and wide-ranging co-operation, with data centres containing an unusually large amount of building-services engineering.

Andrey Blokhin, who is responsible for Nebius’s global infrastructure, said the new site would substantially strengthen the firm’s operations in Mäntsälä. He said Jatke brought experience of large and technically demanding building projects.

Boom in data centres

The contract comes amid a rapid expansion of data centres in Finland. The Confederation of Finnish Industries (EK) estimates that projects at stages from preliminary studies to construction are worth more than €80bn (£70bn).

The grid operator Fingrid has estimated that Finland’s electricity consumption could rise by almost 40% from its 2025 level if every project with a grid-connection agreement were fully carried out.

Ulla Heinonen, EK’s director of green growth, has stressed that data centres’ electricity use will not grow suddenly. She says the market should prepare for rising demand by adding new generation.

Jatke is a privately owned Finnish construction group with about 430 employees. Its turnover in 2025 was about €503m.

White logo of Finnish AI Region (FAIR EDIH). In is written FAIR - FINNISH AI REGION, EDIH
Euroopan unionin osarahoittama logo

Finnish AI Region
2022-2028.
Medialle